Emergency bank (A10)

Dyness 24 V 100 Ah | bought battery, not a built box | GitBoat v10.5 A10

Status notes
  1. Bilge pump wiring Decided

    Bilge pump wiring, 2026-10-31. The sheet is the drawing. Do not copy a channel-12 path through an aft junction onto the page. Pump 1 stays on the main side (line 11, Water Witch, channel 6, opto 1, A3 entry 9). Pump 2 is on the backup battery (Johnson Pump Ultima Switch). Channel 12 is spare. Water Witch 2 is on the shelf.

    Electronics A10: it keeps the boat sailing when the main battery is dead or cut off (why: Design Decisions R-4.3A). It powers Pi B, WD-B, GPS B, IMU B, Iridium B and the lightning detector; bilge pump 2, always (below); and, only when the main side is dead, the backup-fed bar through the backup converter: the central node, steering, the wing box, release bus A and Release Node B (sec 7.6). Pump 2's switch is the Johnson Pump Ultima Switch. The Victron BatteryProtect and the backup converter are on this board. The Victron Orion-Tr 24/24-5 isolated DC-DC is the float charger from the main bus.

    Open: Backup_Battery_Board_Layout_2026-10-15 does not yet show pump 2, the BatteryProtect or the converter's input (Electronics A10). The 2026-10-15 sheet diff adds a BatteryProtect and a pump-2 cut and says updated 2026-11-01. The drawing is not finished.

    Water Witch 2 is on the shelf. Datasheet: docs/reference/Water_Witch_217_230_230-24_Install_Sheet.pdf. The fitted pump-2 switch is the Ultima Switch.

  2. Box plan Decided

    Backup battery board plan. Pump 2 is on this battery. Lines 2, 3, 4, 5 and 14 leave the backup-fed bar. Line 15 leaves this board.

  3. Backup changes Decided

    Pending 517: they draw what the guides already decided (Electronics plan 7.6 and A10; items 487, 489, 490, 501 (e) and (f)); nothing new is decided except Claude's picks below. Both of its shunts sit on the positive side, on the main bus board (sec 7.6).

    Pending 517: the backup battery board is built in a different arrangement from Backup_Battery_Board_Layout_2026-10-15 and the Backup Battery Board plan, so the earlier layout drawings are out of date for it. The photos say both shunts are still on the minus side (item 487 still to do). The guide still puts both shunts on the positive side. Pending 518, where the Argodiode and the backup-fed bar go, stays open and is not drawn.

    Pending 517: both plans are 3 pages each: the photo with numbered marks; the wiring diagram after the changes, added 2026-11-03 at Mike's ask, "can you add wiring detail image?"; then every new or moved wire, the order of work and the parts. This plan's middle page is headed Backup battery board: wiring, page 2 of 3, how it connects after the changes, not to scale, new parts in green.

A10 EMERGENCY BANK | BOUGHT BATTERY | NO BUILT BOX Dyness 24V 100Ah LiFePO4. The unit is the enclosure. No hole schedule.Dyness 24 V100 Ah bought 30 A ANL on the backup battery board, nearest the plus post. No on/off switch: this fuse is the off switch for work (Electronics A10). Red and black bus bars bought 2026-10-15.30 A ANLoff switch Pi B load breaker, 5 A, on the backup board. Auto-reset, no off lever (Electronics A10). No Pi B fuse in the Pi B box.Pi B 5 Ano off lever Iridium B load breaker, 5 A, on the backup board. Auto-reset, no off lever (Electronics A10).Iridium B 5 Ano off lever Victron Orion-Tr 24/24-5, bought ($56.10). Central relay channel 10, normally open, A3 entry 16.Orion-Trch 10 NO Own solar: two 50 W panels. Sixth NanQue PV surge is still to buy, to PV minus, never lightning copper.SmartSolar75/10 Whether the built-in low-temperature cutoff blocks charge only, or discharge too, is open with the maker.cold cutoffOPEN CANH CANL power USB Ethernet UART I2C GPIO coax SPI